NEED A PERMIT…
How Long Will It take?
Below
is a list of "average" time-frames applicants
can expect for an application to be approved for permitting.
Assuming all applications are completed in full with
all required drawings/seals needed with applicable insurance
and bonding forms complete and on file. Applicants should
be aware that project changes, weather and other circumstances
may effect the time turn around for any and all permit
applications.
Most
application forms are not yet available on the INTERNET.
Applicants may contact the individual department for
a faxed copy of a blank form. Applicants could then
fax a completed form to the Department for consultation
on projected "fees". Many permits are based
on the value of the work to be performed also many permits
require "original" attachments before a
permit can be issued.
|
TYPE OF PERMIT |
AVG. TIME |
DEPARTMENT (Floor Number and Quadrant) |
| |
|
|
| Administrative Special Use |
1 week |
Planning/2 East |
| Animal License |
Over the Counter |
Finance/1 East |
| Auction |
1 week |
Planning/2 East |
| Banner Permit |
2 to 3 days |
Planning/2 East |
| Blasting Permit |
3 months |
Public Works/2 West |
| Block Party |
1 week |
Planning/2 East |
| Burn Permit |
1 day (24hrs) |
Fire Dept/Station 3 |
Cereal Malt Beverage& Retail Liquor License |
1-2 weeks |
City Clerk/Council 1 East |
| Day Care Permit |
1 day (24hrs) |
Fire Dept/Station 3 |
| Deck |
1 day (24hrs) |
Codes Admin/2 East |
| Estate Sale |
Over the Counter |
Codes Admin/2 East |
| Fence |
Over the Counter |
Codes Admin/2 East |
| Re-Roof |
Over the Counter |
Codes Admin/2 East |
| Electrical |
Over the Counter |
Codes Admin/2 East |
| Elevator |
Over the Counter |
Codes Admin/2 East |
| Fire Suppression System |
3 days |
Fire Dept/Station 3 |
| Flatwork |
1 day (24 hrs) |
Codes Admin/2 East |
| |
|
|
|
Grading |
| Initial application |
2 weeks |
Public Works/2 West |
| Final application |
Over the Counter |
Codes Admin/2 East |
| |
|
|
| Heating/Air Conditioning |
Over the Counter |
Codes Admin/2 East |
Irrigation Permit (with new house const.) |
1 to 2 days |
Codes Admin/2 East |
Irrigation Permit (with existing house in ROW) |
1 to 2 days |
Public Works/2 West |
| New Commercial Construction |
2 to 3 weeks |
Codes Admin/2 East |
| |
|
|
|
New Development |
| 1st Submittal |
3 weeks |
Public Works/2 West |
| each subsequent submittal |
2 weeks to variable |
Public Works/2 West |
| New Residential Construction |
1 to 2 days |
Codes Admin/2 East |
| Occupational License |
Over the Counter |
Finance/1 East |
| Permanent Sign |
1 week |
Planning/2 East |
| |
|
|
|
Plumbing |
| Commercial |
1 to 5 days |
Codes Admin/2 East |
| Residential |
1 to 2 days |
Codes Admin/2 East |
| Pool/Hot Tub |
1 to 2 days |
Codes Admin/2 East |
| Retaining Wall |
Over the Counter |
Codes Admin/2 East |
| Right-Of-Way |
1 to 2 days |
Public Works/2 West |
| Remodel |
1 to 2 days |
Codes Admin/2 East |
Solid Waste (Trash Haulers) |
2 days |
City Clerk/ 1 East |
Sport Court (with no lighting) |
1 to 2 weeks |
Planning/2 East |
Sport Court (with lighting) |
2-3 months |
Planning/2 East |
| |
|
|
|
Structure Moving |
| State Permit |
Varies along with Traffic Control from Police Dept. |
| Codes Admin. Approval |
1 to 5 days |
Codes Admin/2 East |
| Temporary Sign |
2 to 3 days |
Planning/2 East |
| Tenant Finish |
1 to 5 days |
Codes Admin/2 East |
| Tent Permit |
1 day (24 hrs) |
Fire Dept/Station 3 |
|